Here is a list of the different things we worked on.   Nothing really looks much different, but we did get many different things taken care of.
  • Purchased and installed Microwave
  • Capped old refrigerator water line (to prevent possible leak)
  • Added junction box in crawl space for hanging live wire found by Mr. Sparky
  • Added conduit to breaker box for new range electric supply line.
  • Ran new 8-3 wire for stove from breaker box to new location
  • Mounted new surface mounted outlet for range
  • Fixed water leak from cracked drain line
  • Assembled Lazy-Susan cabinet
  • Removed more old tile.
  • Finalized plans for counter layout
  • Sanded and stained base cabinets (except silverware)
This one passes
What a mess...
Tile removal
New range outlet ready to go

Base cabinets stained.

Water leak fixed

TODO This week:
  • Finish staining and polyurethane base cabinets
  • Order Lazy-Susan hardware
  • Install drawer slides in base cabinets
  • Finish box joint jig and build a drawer
  • Get gas line/stove moved
  • Start tearing out half wall in nook.